| |
May 14,
2007
|
| |
|
| |
UPCOMING MBTA
EVENTS |
| |
Transportation Day at the
Legislature Wednesday, May 23 State House,
Augusta
Transportation Bond
Vote
Tuesday, June 12
Washington County Meeting
Thursday,
June 14
Eastport Chowder House,
Eastport, 5 p.m.
Infrastructure Golf Tournament
Thursday, July 12 Augusta Country
Club, 9 a.m.
Aroostook County
Meeting
Thursday, August 2
Northeastland Hotel, Presque Isle, 5 pm
Fall Convention
Friday, September 14-16
Samoset Resort, Rockport
For more information,
contact the MBTA at (207) 622-0526
| |
|
IN
THIS ISSUE
• MaineDOT biennial work plan details
• MBTA board
voices objections to Sears Island agreement
• Take the
Commuter Challenge for Commute Another Way Week, May
14-18
• Sign up today: Maine Transportation Day at the State
House, Wed. May 23
|
MaineDOT rolls out 2008-2009 work
plan
$815 million plan
does not regain ground lost during past
biennium
MaineDOT has unveiled
its new capital work plan for the 2008-2009 biennium. The plan
carries an $815 million price tag. While that number may seem
impressive after the drought of projects coming out of the
department during the past two years, it comes nowhere near to
getting Maine’s transportation investments back on track. In
Commissioner Cole’s own words, the work plan is
“custodial.”
MBTA has reviewed the plan and found that it
falls short in three major areas: bridges, highway reconstruction
and paving.
Bridges The work
plan calls for the rehabilitation, replacement or painting of 45
bridges. The department’s buying power has been so eroded that
even with this plan’s considerably higher levels of funding, it
does little to address the growing backlog of bridges. With 288
bridges are at risk of failing and hundreds more reaching the end
of their serviceable life, MBTA believes we should be replacing 72
bridges during this period to begin addressing the
backlog.
Highway
reconstruction The plan loses even more ground
when it comes to highway reconstruction. It calls for only 78
miles of reconstruction, almost all of which was deferred from the
last plan or has a federal earmark. The plan does not even restore
all of those projects that had been deferred. Some will be reduced
in scope; others will be put off again. Maine will spend 22
percent less on reconstruction in the new biennium. We will
rebuild only 78 miles when we should be reconstructing 205 miles —
meaning the backlog will grow even larger under this
plan.
Paving When it comes to
stretching money set aside for paving, MaineDOT is being forced to
spread its scarce fiscal resources for paving ever more thinly on
the highway. The new work plan calls for spending $45.6 million
more on paving than the current biennium. But even with the
increased funding, MaineDOT does not have what's needed. The new
plan buys Maine only 1,250 miles of pavement preservation
and maintenance paving using cost-saving thinner
treatments. Once again, Maine will see its backlog of deficient
highways grow. The downward cycle is actually accelerated, because
the thinner treatments have a shorter life
span.
Bonding The plan relies
heavily on the upcoming June bond vote (for $113 million), and a
second bond that will go out the public in June 2008 ($23
million). It is critical that both these items pass in order to
fund the projects in the work plan. It also calls for a $50
million GARVEE (Grant Anticipation Revenue Vehicle) — a bond that
has yet to be taken up by the Maine Legislature.
MBTA will
continue to press the legislature — and voters — to address these
needs through the upcoming bond referendums, passage of stronger
budgets for capital improvements and passage of a longer term fix
through LD 1790, An Act to Secure Maine’s Transportation
Future. Success on these fronts will secure the federal match
of $262 million and local match of $35 million that the MaineDOT
work plan is dependent upon and allow that work plan to be
expanded.
To view work plan specifics, including proposed
investments in freight, transit, ports and harbors, download a
copy of the entire plan at www.mainedot.gov.
|
|
MBTA
board voices objections to Sears Island
agreement
Concerned that agreement
jeopardizes $26 million investment by Maine
citizens
The MBTA board of
directors voted unanimously at its last meeting not to sign the
Sears Island agreement resulting from the state’s Sears Island
Planning Initiative. MBTA members and staff who have attended
meetings and participated in the discussions voiced their
disappointment with the process. MBTA would have been willing to
split the island in half, and pending a permit process, provide up
to an additional 129 acres for preservation once mitigation
questions had been answered.
The agreement cedes 600 acres
to permanent preservation and after a joint use planning process,
allows for an educational center to be built on the island. The
MaineDOT would be able to market a port during this time, but a
majority of the island would be in permanent conservation prior to
the permitting process, placing a cap on port development. This
would mean that needed flexibility would be lost to negotiate such
matters as wetlands mitigation. The MBTA board was concerned with
giving up negotiating flexibility up front before federal and
state regulatory agencies have weighed in as to their
expectations. Board members involved in similar permitting
projects confirmed that it is impossible to predict how many acres
are going to be required for mitigation or preservation by state
and federal agencies – or which acres must be
avoided. The Army Corps of Engineers just
last week revised their requirements, adding to the uncertainty of
the permit process.
Although MBTA board members believe
conservation and passive recreational pursuits can coexist with a
marine transportation operation on Sears Island, they felt it
would be foolhardy to sign an agreement that may compromise
Maine’s use of the Island for marine transportation purposes. No
other location in Maine has the combination of deep water,
available land, accommodating topography and double stack rail
service to the North American continent. With over 900 miles of
the Maine coast already publicly accessible and in conservation –
and only a handful of miles available for marine transportation –
the compelling argument to forever ban the use of two-thirds of
this island for marine transportation has not been made.
|
|
Sign up today • Maine Transportation Day, Wednesday, May 23
• Your
chance to 'talk transportation' with your legislative
leaders
The Maine Legislature's annual Maine
Transportation Day will be held at the State House on Wednesday,
May 23 in the Hall of Flags. Booth space is still available at no
cost for organizations wishing to promote a transportation mode or
project. The day also offers an important opportunity to discuss
issues and concerns with your legislators in a setting that is
devoted entirely to transportation.
MBTA will have a table there, as will
several of our members. Please join us! If you would like to
register for this free event or need more information, please
contact the MBTA office at 622-0526 or deanna@mbtaonline.org. |
Have you
taken commuter challenge? Commute Another Way Week begins
today This week, May 14th -18th,
is Commute Another Way Week. Once again the MBTA joins GO MAINE,
the Maine Turnpike Authority, MaineDOT, the Bicycle Coalition of
Maine and others in sponsoring this statewide event. We urge all
of our members to register either as individual participants or as
employers — and to encourage your employees to get involved, too.
(Yes, you can register to participate right up until Friday, May
18.) It’s free, there are great prizes, and it is an
excellent way to support transportation options in Maine. For
information, visit www.commuteanotherwayweek.org. | |
|